Tonawanda Coke Corporation (TCC) Site
Tonawanda, NY
Tonawanda Coke Corporation (TCC) has operated a coke manufacturing facility at this location since 1978, and the property has been used for the coke manufacturing since 1917. Coke is made by heating coal at high temperatures in the absence of air. On October 14, 2018, TCC suspended operations and initiated process shutdown to permanently close its facility.
EPA in concert with the New York State Department of Environmental Conservation (NYSDEC) led the effort to oversee the safe shutdown of operations involving the 60 coke ovens at the facility. Activities included fully emptying and purging the gases which marked the end of coke production at the facility. EPA assisted NYSDEC in its oversight of facility shutdown activities through air monitoring. The NYSDEC turned the lead over to EPA to conduct a full assessment of the facility and to take actions required to address any risks posed by the facility.EPA’s work at the facility has focused on emergency cleanup activities including the excavation and removal of contaminated soil the treatment and disposal of over a million gallons of waste ammonia liquor, maintaining contaminated secondary containment areas and stabilizing drums, vessels and other containers of hazardous substances. The removal of coal and coke from the facility also continues. EPA has continued to maintain a presence at the Site after the sale of the property.
EPA and the U.S. Department of Justice have worked closely with New York State, local officials and the community in recent years to address violations of environmental requirements at the Tonawanda TCC facility. EPA and the state have worked especially closely with the impacted community in their collective work. The federal government and state have taken multiple actions, including securing a federal Judicial Consent Decree in 2015 (PDF) that detailed the steps necessary for the facility to comply with federal and state environmental law. In addition, the federal government brought criminal charges against the corporation and an individual.
The TCC plant site is approximately 129 acres in size and the nearest residential area is approximately 0.25 miles south of the site.
The site is comprised of two parcels of land separated by River Road. The parcel of the east side of River Road, known as the main plant area, is the portion where coke manufacturing formerly occurred. The parcel on the west side of River Road, adjacent to the Niagara River, is known as Site 108 and is designated by the NYSDEC as a state superfund site.
Air Monitoring/ Sampling
During the shutdown operations at the facility, EPA conducted air sampling and monitoring and surveillance in the community around the plant until all flammable gases were purged from the process systems. Six fixed monitoring locations were selected based on wind direction and/or other factors deemed to be relevant to the health and safety of the public. The purpose of this project was to monitor for benzene, a volatile organic compound (VOC), sulfur dioxide (SO2), and particulates. EPA also collected air samples for quick turnaround laboratory analysis. The monitoring and sampling activities began on October 14, 2018 and were completed on October 21, 2018. Air monitoring and laboratory analysis, as stated in the EPA ERT Air Sampling Report (PDF), indicated that air contaminant levels established to protect the public were not exceeded.
The sale of the TCC property was ordered by the U.S. Bankruptcy Court in September, 2019. The bankruptcy court accepted a proposal from Ontario Specialty Construction and Honeywell International, Inc. for the sale of the TCC property to Riverview Innovation and Technology Campus Inc. (RITC) for the redevelopment of the property as a data center.
In mid-February 2020 the NYSDEC approved RITC’s application to the New York State Brownfield Cleanup Program (BCP) for the cleanup and redevelopment of the main plant. In addition, a new consent order between Honeywell and EPA was executed to address those remaining portions of the TCC Site that had not been admitted into the BCP, referred to as Site 108 which is directly across River Road to the west of the main plant. In the coming months EPA intends to continue to provide oversight of the ongoing work being performed by Honeywell which is expected to be completed by the summer of 2020. Apart from providing oversight of this work at Site 108, EPA has discontinued all other activities at the Site, but remains available to consult with the NYSDEC.
Site Information
- Tonawanda Coke Corporation Community Update, April 2020 (PDF)(1 pg, 136 K)
- News Release: EPA Successfully Wraps Up Activities at Tonawanda Coke Facility, March 2020 (PDF)(3 pp, 403 K)
- Tonawanda Coke Corporation Fact Sheet, December 2019
- Tonawanda Coke Corporation Community Update, February 2019 (PDF)(1 pg, 165 K)
- News Release: EPA Continues Work to Protect Community Near the Tonawanda Coke Facility, Nov. 2018
- Tonawanda Coke Corporation Fact Sheet, November 2018 (PDF)(1 pg, 199 K)
- News Release: EPA Begins Assessment of Tonawanda Coke Facility as Shutdown Operations Wrap Up, Oct. 2018
- Judicial Consent Decree - May 2015
Your Community Involvement Coordinator
Michael Basile
Community Involvement Coordinator
186 Exchange Street
Buffalo, NY 14204
(716) 551-4410
[email protected]
or
Shereen Kandil
Team Leader, Community Affairs
212-637-4333
[email protected]